Each of the racks in the AKCP test data center will be equipped with 3x 9kW space heaters to simulate servers. This allows us to operate at 27kW per rack. … Read More
Sheet rock delivery and insulation update
Today the sheet rock for the stud walling was delivered, and insulation was starting to be installed. It is important that we make sure the data center is well insulated … Read More
Delivery of the Racks
We took delivery today of the first order of 42U racks. These are open frame racks, perforated front doors. We will begin fitting these out with space heaters, AKCP RFID … Read More
Construction Update – Stud walling frame work
The stud walking frame work is almost done, the layout of the room is starting to take shape.
Construction Begins!
Materials for the partition walling has been delivered and the contractor has started the work. Foam insulation was also delivered. The walls will be constructed from metal studs, with outer … Read More
Delivery of 250kW Generator
Today we had delivery of a 250kW generator. The first step in our construction of the test data center was to bring in power. As the utility company could not … Read More